I was looking at the Project Server 2010 October 2011 CU today, and I noticed something noted towards at the end of the article, which piqued my interest.
In Project Server 2007, the task updates from resources, would be highlighted in red. However, when Project Server 2010 came out, this feature was sorely missing. All updates (previous and current) would all look the same, making it difficult for the approver to identify which updates were new easily. See below for example.
This has been brought up by more than one of my customers.
With the Project Server 2010 October 2011 CU, this is fixed. After Installing this update, the Task Updates are highlighted in the approval center now.
I guess, this will make one more thing easier in Project Server 2010 to use.